Renovations are exciting for the visible bits: the kitchen, the flooring, the colour on the walls. The electrics are none of those things, which is exactly why they get left until last, and why so many homeowners end up chasing cables through walls they’ve just had plastered.
The rule is simple. Decide the electrics before the decorating, and ideally before the plasterer is booked. Here’s why, and what to think about.
Why the order matters
Electrical work in a renovation is almost all “first fix”: cables run in walls, ceilings and floors before the surfaces go on. Once the plaster is skimmed and the paint is up, every extra socket becomes a chase, a patch, a repaint and a bill. The cheapest time to add a circuit is when the walls are open. The most expensive time is a week after you’ve finished.
That applies whether you’re refitting a single room or gutting the house. If the plan includes a full or partial rewire, the ordering matters even more, because the rewire sets the layout of everything that follows.
Does the house need a rewire?
Not every renovation needs one, and rewiring isn’t mainly about fixing faults. It’s about bringing an old installation up to the standard a modern home needs. Signs that a rewire should be part of the project include:
- Original wiring in an older property, especially cables with no earth conductor on the lighting circuits.
- Old cable colours and a consumer unit that predates RCD protection.
- Far fewer sockets than you’d actually use, with extension leads doing the rest.
- An extension, loft conversion or open-plan reconfiguration that changes where everything needs to be.
An Electrical Installation Condition Report before the project starts is the cleanest way to answer the question. It tells you what’s there, what’s safe, and what’s worth keeping.
Room by room: what to decide early
Kitchen. The most electrically demanding room in the house. Appliance positions, the cooker circuit, under-cabinet and plinth lighting, island sockets, and where the extractor goes all need settling before the kitchen fitter turns up. We’ve covered this in detail in our kitchen electrics guide.
Bathroom. Bathrooms have strict rules about what can go where. Shower circuits, extractor fans, lighting and any heated mirror or towel rail need designing to those rules, not squeezed in afterwards.
Living spaces. Think about where the TV actually goes, whether you want a media wall, where lamps will plug in, and whether you’d like lighting on more than one circuit so you can dim a room down in the evening.
Bedrooms and home office. Sockets either side of the bed, USB outlets, and a dedicated circuit if a room is becoming a full-time workspace.
Outside. If there’s any chance of a garden room, hot tub, EV charger or decent outdoor lighting in the next few years, get the cable run in now while the ground is already up.
The consumer unit
A renovation is the natural moment to upgrade the fuse board. New circuits need space on the board, and a modern consumer unit with RCBOs on every circuit and surge protection gives the finished house the protection it deserves. It’s far easier to do while everything else is being done.
Paperwork and certification
Much of the electrical work in a renovation is notifiable under the building regulations, which means it either goes through building control or is self-certified by a registered electrician. DW Electrical Solutions is NAPIT approved, so the certification and notification are handled as part of the job. You’ll want those certificates when you sell.
Getting the sequence right
Talk to your electrician at the planning stage, not the plastering stage. Bring the drawings, the kitchen plan and a list of what you want each room to do, and let the electrics be designed around the finished house rather than retrofitted into it.
DW Electrical Solutions works with homeowners renovating across Hampshire, from Fareham and Portsmouth to Winchester and Southampton. Get in touch to discuss your project.