Short answer: yes. A house can be rewired in stages, and plenty of Hampshire homes are. Whether it is right for yours depends on the state of the existing wiring, what you are planning to do to the house, and how much disruption you want in one go. Here is how staged and partial rewires work, when they make sense, and when they cost more than doing it all at once.
If you are still weighing up whether a rewire is needed at all, start with our guide to why full or partial rewires matter. This post is about whether it has to happen all in one hit.
Partial rewire or staged rewire: what is the difference?
A partial rewire replaces some of the installation and leaves the rest. A common example in older houses is replacing the lighting circuits, which often have no earth cable, while leaving newer socket circuits that are sound and already protected. The circuits that stay are fully tested and included on the Electrical Installation Certificate, so you have one document covering the whole installation rather than just the new part.
A staged rewire is a full rewire split into phases: downstairs this year, upstairs next, or room by room as each one is renovated. The end result is a completely new installation; it just arrives over a longer period.
Both are legitimate. The key is that every stage is planned as part of a whole, so the circuits, cable routes and consumer unit end up where a full rewire would have put them, rather than becoming a patchwork.
When staging makes sense
Rewiring in stages suits homes where the renovation itself is happening in stages. If you are refitting the kitchen this year and the bathroom in two years’ time, it makes sense to rewire each area while it is stripped out, because that is when the walls and floors are open anyway. Our guide to why electrics should come first in a renovation explains that ordering.
It also suits houses where only part of the installation is old. Many homes have had an extension or loft conversion wired properly in recent years, sitting alongside original circuits elsewhere. There is no need to rip out good work to replace the old; a partial rewire targets what needs modernising and leaves what does not.
And it suits people who want to spread the work, and the budget, over time. That is a perfectly good reason, provided the plan is drawn up at the start.
Living in the house while it happens
The question behind the question is usually “can we stay at home?” Yes. In an occupied house the existing cables, sockets and lights stay live while the new installation goes in alongside them. The switch-over happens near the end of each stage, and only then is the old wiring removed, so you keep fully or near-fully working electrics throughout.
Each stage involves some dust, so we prepare properly: dust sheets down, furniture wrapped, and the house hoovered and floors wiped before we leave. If a plasterer is not already booked, we can make good the chases ourselves so you can get straight on with decorating. Our guide to what to expect during a rewire walks through a stage from survey to certificate.
When staging is a false economy
Staging has two drawbacks worth knowing before you choose it.
The first is the consumer unit. New circuits need a modern board to connect to, with RCBOs on each circuit and surge protection, so the new consumer unit goes in at the first stage. Where possible we fit it alongside the old board rather than replacing it: the old circuits stay on the old board until their turn comes, each new circuit moves onto the new board as it is finished, and the old board is removed and made safe at the very end. It does mean the first stage carries more of the cost.
The second is repetition. Each stage means floorboards up, chases cut, making good and decorating in that area. If the whole house is going to be decorated in one go anyway, rewiring it in one go before the decorating starts is almost always cheaper and less disruptive than coming back three times.
A good rule of thumb: stage the rewire if the renovation is staged. If the house is being redone all at once, rewire it all at once, before the plasterer and the decorator.
Getting it planned properly
Whichever route you take, the plan comes first. A survey shows what is sound and what is not, and an Electrical Installation Condition Report is the cleanest way to get that picture if you are unsure. From there we set out which circuits each stage covers, where the new cable routes and consumer unit go, and what gets tested and certified at the end of each phase. Because DW Electrical Solutions is NAPIT approved, the work is certified as it goes and notified to building control once the installation is complete, so the paperwork joins up when you come to sell.
DW Electrical Solutions carries out full and partial rewires across Hampshire, from Portsmouth and Fareham to Eastleigh, Romsey and Winchester. Get in touch to discuss your project.